US20050155297A1
2005-07-21
10/760,335
2004-01-20
A construction system for massive dwellings or alike; a unit shall be built in 5 days after preliminary work. First, shall be prepared precast items: sills and headers, using templates and reinforcing them to resist shear and diagonal stresses; and exterior and interior wall molds to use numerous times. Then foundation shall be set to have a slab floor with pipes inside a steel structure, and wall molds erected on each side of it, following a predetermined color and graphic code. Afterwards, shall be inserted precasts and all openings of building to pour concrete masonry and form a monolithic structure. A steel structure shall be embedded on top of walls for anchoring concrete T-beams. A material to insulate and form a stem of said T-beams shall be put on platform surface, and then a metallic mesh for reinforcing said T-beams, and for setting pipes, lastly, concrete shall be poured over.
Get notified when new applications in this technology area are published.
E04B1/161 » CPC main
Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs; Structures made from masses, e.g. of concrete, cast or similarly formed with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material with vertical and horizontal slabs, both being partially cast
Not applicable.
STATEMENT REGARDING FEDERALLY SPONSORED RESEARCHNot applicable.
REFERENCE TO A SEQUENCE LISTING, A TABLE OR A COMPUTER PROGRAM LISTING COMPACT DISC APPENDIXNot applicable.
BACKGROUND OF THE INVENTION1. Field of Invention
This patent application falls in the “Construction System's” field. It is a method to produce massively dwellings or any buildings at an affordable cost from preliminary planning to all other construction steps: foundation, walls, roofing, finishing, cleaning and delivering. The System is using several prior arts, which are improved and combined together to accomplish a method capable to produce high volumes of dwellings at an affordable cost, and in a short lapse, and without employing expertise labor.
2. Description of Prior Art
(a) Masonry Wall Construction
Masonry wall construction is a very old building practice; in the Greek island of Thera (known as Santorini) the mortar used was the local volcanic soil. This practice was successful but slow.
In the Imperial Rome, the inventive mind of the Romans and the availability of volcanic sand with cementing properties, crafted a mortar to cast masonry with natural stone, or ruble from demolition; the Pantheon in Rome, built circa 123 A.D., is one among many still standing in our era. Although Romans accomplished such long standing constructions using a system of “lost molds” (two parallel brick walls for casting masonry,) had to withstand a time-consuming production since these brick molds were incapable to hold the lateral forces of all the liquid mortar necessary to fill said lost molds to the expected height in one pour, as a result was done in rows after rows. Furthermore, this system was possible because slavery was legal in Roman times, so a titanic inexpensive labor crew was feasible for handling too heavy duties.
(b) Conventional Masonry Construction, Currently Used.
This system calls for several construction materials, such as stone masonry, concrete blocks, clay bricks, and the like to build walls. The construction must be coordinated with the footing construction, and a qualified labor as well as supervision to perform several demanding tasks.
Besides, after walls have been built, electrical, plumbing pipes, and outlets are installed, consequently said walls are later on scoured and patched. Furthermore, headers for door and window openings, and door and window frames must be put, having one make use of more construction supplies that in time get cracks in between, so their exterior perimeter have got to be caulked and maintained.
In addition, delivery of materials and their reception with all the clerical work involved has to be handled, making the whole process time consuming and highly costly.
(c) Wood or Metallic Framing Walls.
The framing construction requires qualified labor and close supervision of anchors, especially for certain sections of walls capable of resisting earthquakes.
Connecting metallic members with nails or setting directions is difficult, that on occasions workers who do not understand instructions skip them and supervisors do not notice that omission, and as a consequence the desired quality of the structure is not quite accomplished.
Although metallic framing is better than wood framing regarding termites and flammability, requires more specialized labor and tight supervision making the system expensive.
Further, to make walls from both framing systems it is needful to plaster exterior or apply a siding material on perimeters, and for an interior face and partition walls gypsum board is normally used. Thereafter a furring process which requires specialized labor, plus shear reinforcement and installation of windows and doors with all the complications of caulking, flashing and leveling. Whilst, if insulation is required, rigid insulation is expensive to use and blanket insulation requires wider depth for higher values, condition which asks for an increase in the width of the walls, as the items used called studs need to be wider, or use a double framing and a rise in costs.
Finally, delivery and reception of materials need lots of clerical work, causing time consuming and all the process is highly costly.
(d) Prefabrication System.
Prefabrication involves lots of materials: steel, aluminum, wood, panels of combined materials including plastics, and even concrete, mainly light weight concrete. Moreover to assemble a building using prefabricated elements encompass several conditions because of being produced by industrial means, increasing costs and making such system more fancy than effective.
It also requires a factory, specialized machinery, technical personnel, and a market absorbing the planned production, and enough storage space for the elements in stock, as delivery of materials and reception with all clerical work involved.
All the process is time-consuming and complex, since fabrication limits the amount of units to be built as availability of elements is the function of the factory's production. This system cannot solve a high demand of dwellings for a disaster solution.
As a final inconvenient point, design solutions depend on the modular dimensions hence, limiting innovation, flexibility, and functionality.
BRIEF SUMMARY OF THE INVENTIONThe present invention is aimed at producing massive amounts of dwellings and the like, sorting the positive advantages of reliable prior arts, and coordinating, and translating them to our present times to produce strong, monolithic enclosures at an affordable cost, which overcomes the foregoing drawbacks of the conventional arts after a combination and improvement of them.
It is an object of the present invention to provide a method, based on concrete masonry and precast concrete accessories, a construction lapse compressed in five days for one building unit, as follows:
The set of molds of each phase: foundation, walls, and roof shall be moved to the next site every day; thus, shall be produced a finished building every day from the fifth day of starting the construction. The number of units delivered a day shall depend on the number of sets of molds to be used.
ADVANTAGES OF THE PRESENT INVENTIONThe use of the present invention not only will provide housing and related buildings to a world wide exploding population at a fair cost.
The present invention starts the construction process by obtaining information of the working conditions and requirements, in order to do a specific design and plan of action. Consequently, an open forum of discussion for the design solutions regarding budget and time frame, evaluating resources and geographical limitations for example weather and seismic conditions. Traditional and social constraints will also be considered. All this intellectual and technical implementation in comparison with other construction systems, which only follow traditions without making the players part of the solution, provide a further education for the personnel involved in the use of the present invention.
Another object of the present invention is to provide the necessary training to the work force in order to use efficiently the system, creating a new working expertise and education skills which can improve the social environment of the workers, and related personnel to the construction process.
Another object of the present invention is to provide special precast items such as headers, and sills to complement windows and doors openings. These precast items lower costs and increases speed with high results in the construction process.
Another object of the present invention is to design a set of wall wood molds, using traditional techniques, but with improvements which when utilizing every day can be used 30/40 times.
Another advantage of the present invention is to provide a low cost in maintenance because concrete masonry is waterproof, for this reason, no oxidation risks arise providing a long lasting performance. What's more, no termite attacks; and no use of construction materials as lumber, thus, natural resources undermining is avoided.
Another advantage of the present invention is to provide the possibility to build walls with all the ginger bread, when desired by the user, and no additional specialized labor or cost. Since one of concrete's attributes is that it molds into any shape of any special mold, creating a final structure that has the shape, line and volume of any dimension one may require.
Another advantage of the present invention is to provide no limitation of shape, size, or functionality; as walls can be of any desired thickness, appearance, and functionality; and alcoves to contain insulation materials can be added, etc.
Another advantage of the present invention is to provide a strong and light roof structure of reinforced concrete, type known as T-beams, which uses a small volume of concrete to cover a comparable long span.
Another advantage of the present invention is to provide a cost reduction in improving the thermo function of the roof, by using either insulation or alternate material to form the T-beams' stem.
Another advantage of the present invention is to provide a place to embed electrical, plumbing or other pipes protecting these main elements from damage as a consequence of using reinforcement for the concrete.
Another advantage of the present invention is to provide an earthquake, fire; termite, hurricane, and flooding proof construction due to concrete masonry's characteristics, and the monolithic nature of the structure.
All the foregoing advantages distinguish the present invention as a powerful construction system of dwellings and the like, in improving and combining prior art, besides, introducing some new items and concepts. Giving the building industry worldwide the opportunity to satisfy the need of affordable constructions at massive production levels.
Furthermore, another important advantage of the present invention is that it has no limited scope regarding building type; as it is fitting for the construction of dwellings, schools, commercial buildings, offices, and medical services, hotels, etc., one level or multiple stories, and can be simple or trendy according to the ability of who designs the particular architectural style. The use of the present invention will improve the construction industry worldwide, creating jobs and increasing business in massive numbers.
BRIEF DESCRIPTION OF THE SEVERAL VIEWS OF THE DRAWINGSThe foregoing Summary as well as the following Detailed Description of Preferred Embodiments is better understood when read in conjunction with the appended drawings. For the purpose of illustrating the invention, there is shown in the drawings embodiments which are presently preferred. It should be understood, however, that the invention is not limited to the specific methods and instrumentalities disclosed.
FIG. 1 is an exploded isometric view of the preferred embodiments of the present invention.
FIG. 2 is isometric sketches of precast items, and anchor structure.
FIG. 3 is a series of sketches of the operations to produce the footings and floor slab in the first construction day.
FIG. 4 is a series of sketches of a construction sequence to set the wall molds.
FIG. 5 is a series of sketches of a construction sequence to install windows using the precast sill and header before pouring concrete masonry for walls.
FIG. 6 is a series of sketches of a construction sequence to install doors: exterior or interior using the precast header before pouring concrete masonry for walls.
FIG. 7 is a series of sketches of a construction sequence to pour the masonry concrete into the walls in the second day of construction.
FIG. 8 is a series of sketches of a construction sequence in building a T-beam roof, and rigid insulation or hollow concrete blocks are used to mold the stems.
FIG. 9 is a bar graphic describing times and actions to accomplish the construction of a dwelling unit in five days
No more drawings are necessary, because the following fourth and fifth day of construction, are used to install bath and kitchen fixtures, glazing, painting, flooring, roof waterproofing and details. This part of the construction uses conventional systems.
DETAILED DESCRIPTION OF THE INVENTIONTo facilitate the understanding of the drawings and/or written descriptions, a key number is listed below:
1. Foundation
2. Concrete Masonry Walls
3. Roof (Proposed in the Present Invention)
4. Precast Header
5. Precast Sill
6. Anchor Structure
7. Perimeter Foundation Molds
8. Exterior Wall Mold
9. Wales
10. Bracing
11. Plumbing Pipes
12. Electrical Pipes
13. Interior Wall Mold
14. Ties
15. Wedges
16. Scaffold
17. Rocks
18. Concrete
19. Wood Stick
20. Trapezoidal
21. Graphic Representation of an Exterior Wall Built with Concrete Masonry, used in FIG. 8.
22. Graphic Representation of an Interior Wall Built with Concrete Masonry, used in FIG. 8.
23. A Conventional Structure of Posts and Beams
24. Rigid Insulation
25. Concrete Masonry Units (CMU)
26. T-Beam Reinforcement
27. T-Beam Metal Mesh Reinforcement
28. Window
29. Exterior Door and Frame
30. Interior Door and Frame
31. Waste Lines under Concrete Slab
32. Painted Sloping Strip Marks in Molds
33. Returns
34. Precast Reinforcement
35. Metallic Elements
36. Drilled Holes
37. T-Beams
38. Curing
39. Trowel Finish
To use the present invention the process starts with the listing of the program's requirements regarding:
The present invention massive CONSTRUCTION SYSTEM at an affordable cost based on the use of concrete masonry and unskilled labor to produce dwellings and the like.
The present invention shall use concrete masonry 17+18, and the proposed molds 7 specially designed to produce one foundation unit per day. Said molds shall be used in an automatic manner thanks to a color code 32 (a detailed sequence of steps to build foundation and related elements marked on said molds) refer to FIG. 3.
Walls 2,
The present invention shall built a solid continuous surface using concrete masonry 17+18, (see FIGS. 4 and 7 for detailed information of placing molds and pouring concrete masonry) according to the geographical location by adjusting its shape and process in building, as availability of construction materials, climate variations, seismic forces, flooding, etc. shall be considered. Penetrations of doors and windows are discussed in detail FIGS. 5 and 6.
Also the Construction System in the present invention can be customized to a certain economical circumstances such as a limited budget, and a social and/or ethnical architectural style, and to a critical condition which is the availability of the construction materials and labor.
Regarding the foregoing the present invention as a Construction Method shall not be limited to the physical characteristics shown in the attached drawings, but shall use technical knowledge in general to solve any special circumstances to provide a solution in building swiftly and at an affordable cost to satisfy the needs in whatever construction site.
Roof 3,
Construction in the present invention shall be with concrete 18 T-beams 37, a shape that can be obtained using rigid insulation 24 when required; or hollow concrete blocks 25 for places with mild weather; or factory produced fiber glass molds to create a coffered shape.
An alternate roof construction of lumber, wood trusses, thatched on three branches, etc. can be used, with a simple change in the anchoring connection used for holding roof structure on top of the concrete masonry walls.
For a better understanding of the process it shall be divided into five sections:
1.—Preliminary Work
As follows:
At first shall be carried out discussions about the Construction Method with the personnel in charge of the construction to set conferences for training labor, because it is important the labor personnel understand how their work shall contribute to the success of the aim, and to clarify the construction techniques contained in the present invention because they are different in approaches and goals from conventional ones. Also, to enhance the idea that the present invention approaches massive construction in a short time, and the goal is to build affordable dwellings or any building. Locating and designating an area to produce all precast or preassembled items needed for the invention shall be done, to have the present invention running swiftly.
(See FIG. 2) Precast items: headers 4 and sills 5 shall all be made of reinforced 34 and concrete 18, in the designated area referred above.
(See FIG. 4) In the preliminary task for wall molds, exterior 8 and interior 13, holes 36 shall be drilled into panels of plywood, normally of four by eight feet, and then shall be nailed three 2Ă—4 wales 9 to reinforce 8. Different location of holes 36 and dimensions of the plywood, as well as dimensions and number of said wale 9 shall depend on the walls' width, height, location, and/or special constraints, or uses of the building to be built.
2.—Foundation
Actual construction starts with the foundation for one unit. See FIG. 3, as follows:
(FIG. 3A) Grading levels. A similar shape and form of the ground under and surrounding the constructions shall be required to let rainwater ran freely without going inside the building.
(FIG. 3B) Waste lines 31 under concrete slab. An excavation shall be required to have trenches for installing pipes that trap waste for cleaning purposes or disposal of feces and urine.
(FIG. 3C) Said waste lines 31 set in place. Said pipes shall be installed on the slope to connect end of the line to a main waste line or septic tanks, depending on the infrastructure available at the construction site.
(FIG. 3D) Placement of exterior perimeter molds 7. By following the instructions discussed in the conferences of Preliminary Work and considering the location of buildings in drawings. Said exterior perimeter molds 7 for first building shall be set by a trained supervisor, using dimensioning and leveling tools, and the next ones shall use the first one as datum for a swift placement of the molds 7. This and other tasks are the items for discussion and understanding in the said Preliminary Work.
(FIG. 3E) It shall be dug trenches following the perimeter molds 7.
(FIG. 3F) It shall be dug trenches for interior footings following painted marks 32 located on said molds. The depth of the trenching shall be enough to retire contaminated soil, whilst earth from the excavation shall be deposited in between trenches.
(FIG. 3G) Trenches shall be filled with one layer of big rocks 17 to give room for the next task.
(FIG. 3H) Concrete 18 shall be poured on said rocks 17 using concrete vibrators to make said concrete move in between said rocks, filling voids.
(FIG. 3I) Operations (g) and (h) shall be repeated until reaching eight inches (20 centimeters) plus o minus below the top of the perimeter of said molds.
(FIG. 3J) A layer of rocks 17 shall be placed on the area in between footings, these rocks can be of any dimension as long as when laid down form a flat bed and after a concrete mat is poured forms a slab floor of around four inches high, a horizontal finish floor level. This layer works as a cushion in case of an expansive soil condition. Expansive soil, has the characteristic of reducing greatly its volume when dry, but comes back bigger with moisture. This condition breaks the concrete slab floor very easily. In the General art metal mesh is used, similar to 27; but in the present invention shall be used rock beds, which guarantee space for soil volume changes and works better than a conventional metal mesh.
(FIG. 3K) A structure of rebars and stirrups 6 shall be half embedded on said perimeter molds 7 when the concrete is still soft, leaving open spaces for doors and sills, as marked by the color code 32.
(FIG. 3L) Lastly, the floor surface shall be smooth with a metal hand tool named trowel 39.
Then, cured 38 with clean water after the floor slab is hard enough to traffic without showing marks. A water hose can be used.
3.—Walls.
Construction of walls, see FIG. 4, as follows:
(FIG. 4A) One side of wood molds 8 shall be erected, this mold is the one reinforced with three wales 9 of a 2Ă—4 (5Ă—10 cms. nominal) wood and nailed, to keep molds aligned, and shoring elements 10 shall be used to brace and to straighten them into a perfect vertical position.
(FIG. 4B) Once the wall molds are in place ties 14 separators for assembling wall molds, shall be inserted into the pre-drilled holes 36 of the molds 8.
(FIG. 4C) Then, ties 14 shall be inserted into the pre-drilled holes 36 of molds 13.
(FIG. 4D) Wedges 15 shall be used at the two ends of ties 14 to tighten together said molds 8 and 13. At this point said molds for solid walls shall be ready for concrete masonry pouring. This operation of pouring walls with concrete masonry is shown in FIG. 7.
For window placement see FIG. 5.
(FIG. 5A) It is an exploded sketch showing precast sill 5 that shall be set against and in between nailed wood return pieces 33 of molds 8. The window 28 shall be placed on top of sill 5.
(FIG. 5B) It is an exploded sketch showing said precast sill 5 against and in between said nailed wood return pieces 33 of said molds 8. Said window 28 shall be placed on top of said sill 5.
(FIG. 5C) It is an exploded sketch showing said precast sill 5 against and in between said nailed wood return pieces 33 of said molds 8. Said window 28 is now on top of said sill 5.
The two molds 13 are shown in an exploded position. Note that all wall molds do not show holes 36 or wales 9 or braces 10 but all these elements shall be present and used as before stated in FIG. 4.
(FIG. 5D) It is an exploded sketch showing said sill 5 against and in between the 33 of the 8. The 28 is on top of said 5, said two molds 13 as shown in place, too, however, all wall molds shown do not show said holes 36, said wales 9, either said braces 10, ties 14 and wedges 15, which shall be used to tight said 5, and said 28. Precast header 4 shall be set on top of said 28 and in between said 33 attached to wall said 8 and the 13 as shown in an exploded sketch. Note that said 33 have the double function of holding precast items and window or door frames, and they are a stop forming the ends for the concrete masonry in between openings.
Door placement, see FIG. 6, as follows:
(FIG. 6A) It is an exploded sketch showing door 29 or 30, an exterior or interior door, which are similar, that shall be set against and in between nailed wood return pieces 33 of molds 8.
(FIG. 6B) It is an exploded sketch showing said door 29 or 30, against and in between nailed said wood return pieces 33 of said molds 8.
(FIG. 6C) It is an exploded sketch showing the 29 or 30, against and in between the 33 of the 8.
Molds 13 are shown in an exploded position, too. Note that all the wall molds shown do not show holes 36, wales 9, either braces 10, however all these elements shall be present and used.
(FIG. 6D) It is an exploded sketch showing said 29 or 30, against and in between said 33 of said 8. Said 13 are shown in position holding said 29 or 30. Note, once more all said wall molds do not show the 36, the 9, either the 10, ties 14 and wedges 15, which shall be used to tight said 29 or 30. The precast header 4 is shown in an exploded sketch; it shall be on top of said 29 or 30 and in between said 33 attached to said 8 and 13. Said 33 have a double function: hold the precast items and said 29 or 30, whilst they also are a stop forming the ends for the concrete masonry in between openings.
Pouring concrete masonry into molds of walls, see FIG. 7, as follows:
(FIG. 7A) After bracing and verifying the plumb of the molds scaffold 16 shall be set and rocks 17 shall be put on the scaffolds to do the pouring.
(FIG. 7B) Concrete masonry cast into said molds shall start by filling said forms 8 and 13 to two feet eight plus or minus of concrete 18 (a mixture of cement, gravel, sand, and water at appropriate proportions to have a 5000 pounds per square inch), a resistive quality.
(FIG. 7C) Once said two feet eight of concrete 18 are inside the molds, said rocks 17, which must be one dimension smaller than the distance in between said forms, shall be pushed using a 2Ă—4 stick 19 into the soft concrete, one after another, until no said concrete is covering the top of said rocks. Then a second layer of concrete shall be placed on top, and another layer of rocks pushed once more into said soft concrete. The filling does not need to be in all said forms at the same time, the pouring can be advancing, thus a layer of 10 feet in length shall be poured into a form end and said layer is not even in width but instead of an approximate 45 degrees slope, to have rocks pushed into; and after that another layer of 10 feet in length shall be poured besides the first to have rocks also pushed into, and over again, till the bottom of the forms is covered with one layer of concrete masonry and ready for the next. This helps to avoid concrete hardening and the next masonry placing shall have a strong bonding.
(FIG. 7D) After filling said forms to the top, and before said concrete starts hardening, structures of rebar and stirrups 6 shall be half embedded at the top of the walls.
(FIG. 7E) An alternate option, in case lumber or metal roof structures shall be required, a screw item 20 shall be embedded instead at the top of said walls.
Once completed the foregoing operations, the work for the day is done, said concrete shall be dry in the following day and said molds shall separate from said concrete because of a chemical reaction, a loss in water reduces its volume, liberating itself from said forms. Therefore said forms shall be easy to move onto the next wall forming.
4.—Roof
Construction of roofs, see FIG. 8, as follows:
(FIG. 8A) This sketch shows a section of two exterior walls 21 connected to a footing with a structure 6. Another structure 6 is half embedded as shown on top of said walls 21 that shall anchor concrete T-beam 37. Also, the sketch shows one interior wall 22 in between said exterior walls with a structure 6 half embedded on top to anchor the concrete and form a solid connection with T-beam 37 (shown in sketch 8E.)
(FIG. 8B) This sketch shows the same section of 8A, plus a conventional structure of posts, beams and a platform of panels, all under number 23 (wood forms for supporting a construction of concrete slabs), in an schematic representation where bracing and base supporting posts are omitted for clarity.
(FIG. 8C) This sketch shows the same section of 8B, with said conventional wood forms 23 for supporting concrete slabs. The surface of platform 23 has on top rigid insulation panels 24. The panels form a stem of said T-beams 37 (shown in sketch 8E) and also provide temperature insulation to the roof
(FIG. 8D) This sketch shows the same section of 8B, with said conventional wood forms 23 for supporting concrete slabs. The surface of platform 23 has on top an alternate option, hollow concrete blocks 25. This option can form the stem of said T-beams 37 (shown in sketch 8E) and also provide temperature insulation to the roof instead of said panels 24.
(FIG. 8E) This sketch shows a blow up section of the supporting platform 23, and the stem forming/insulation, which can either be 24 or 25 as above mentioned in (8C) and (8D). In addition, shows a metallic mesh 27 used for reinforcing the slab that is part of said T-beams 37. Said slab shall also be used to install plumbing and/or electrical piping, embedded into concrete 18 of said T-beams 37. The triangular shape embodies steel reinforcement structures 26. The broken line represents the top of said concrete 18 that shall be poured in the next operation, when all the foregoing elements are in place. The ellipse marks one T-bar 37 as one unit, which connects with the others to form all roof 3.
(FIG. 8F) This sketch shows the roof 3 after top of surface was smoothen with a trowel finish 39. The sketch also shows a hose pouring water for curing 38 after said trowel finish 39 and when said concrete 18 is still soft but supports traffic.
The day after, 23 shall be moved to the next construction site to keep up with the work schedule. This is possible because the concrete shall be mixed with chemical additives to accelerate the hardening chemical reaction (there are several brands of additives in the market). Furthermore, instead of concrete 18 a fast set Portland cement can be used if available at the construction site. Engineering calculations for laying down the proportions of Portland cement, sand, gravel, water and chemical additives shall consider moving a supporting platform the day after concrete pour. Also, in the present invention shall require the reinforcement 27 with bolder re-bars than the ones necessary when supporting a platform for seven days, as in the conventional systems, however, using them for one day in the present invention reduces cost.
5.—Finishing.
The subsequent operations of painting, installation of bathroom and kitchen fixtures, glazing, details and others, are performed under any methods being used in the area of the construction site, therefore, no mention is necessary. However, it is worth mentioning that female labor shall be used for these tasks because they are better in details and thus, more effective in finishing tasks and it can improve the economy by giving job opportunity to women.
From the foregoing description, it can be seen that the present invention comprises an easy and swift construction system of buildings. It will be appreciated by those skilled at the art that this is for covering any architectural structure under any specification of use or architecture style. Although, the foregoing illustrated the basic material for masonry construction as rocks, it can be substituted by another material available in site, for example coconut shells, rubble from former buildings destroyed by wars or natural causes as earthquakes, or others, even old rubber tires. The function of the basic material is to reduce the volume of concrete used. However, the advantage of concrete is that it can be controlled, as the resistive stress can be customized by calculations of proportions of its components: sand, gravel, cement and water.
It is understood, therefore, that this invention is not limited to the particular construction material and shapes disclosed, but is intended to use the material of construction in site, and any specification or style of construction defined by the appended claims.
It shows a work schedule in a simple tabular form of a process to build 40 units with a set of forms. Serving as the base to figure out how many sets are necessary to build the desired number of units in an expected time frame for a specific job.
I. A construction system for constructing massively dwellings or of the like, that shall be at least in 5 days after preliminary work using rock masonry, comprising:
(a) preparing precast items, sills and headers for window, and sills and headers for doors using templates for,
(b) making wood molds, which can have any chosen shape and size, thereby accommodate any type of opening of a building,
(c) pouring into said wood molds concrete, and after said concrete hardening,
(d) reinforcing the precasts with two rebars, one said rebar shall be at least one and a half inches from the top of said precasts, and the other one at least one and a half inches from the bottom of thereof, so the reinforcement fulfills the function of beams, thereby said precasts shall resist shear and diagonal stresses, and in the intervening time,
(e) drilling holes to exterior and interior wall molds, the molds can be at least of panels of plywood, approximately of four by eight inches, and to said exterior wall molds shall be nailed wales to of about two by four, to be used numerous times in constructing numerous building units,
(f) preparing one of various foundations where trenches are dug using a color code of perimeter molds,
(g) filling said trenches with one layer of the rocks that are poured over concrete to form a slab floor which guarantees space for soil volume, and before concrete hardening
(h) embedding a structure of rebars and stirrups on the perimeter for setting pipes of at least plumbing, electrical lines, telephone lines, and television cable inside, thereby protecting them against rock masonry, and also for anchoring wall molds
(i) erecting exterior wall molds following a predetermined color and graphic code to dispose the wall molds into their correct position, and using shoring elements to straighten said wall molds into a perfect vertical position, on one side of the structure and on the other side is erected interior wall molds following said predetermined color and graphic code, and inserting ties of said exterior mold into said interior molds to tighten both together, thereby said structure is sandwiching said exterior and interior molds and ready for
(j) inserting the precast sill against and in between returns, on which is placed a window, and on which is placed the precast header,
(k) placing a door against and in between returns, on which is placed the precast header, thereby, holding all the foregoing items, and the walls are ready for,
(l) pouring into said walls concrete masonry, and before said concrete hardening,
(m)embedding a construction material on top of walls for anchoring concrete T-beams and firmly connect thereof to said walls,
(n) setting on top of platform of a roof a material for providing temperature insulation to roof and forming a stem of the T-beams, thereby, overriding the cost of forming stems of said T-beams, and
(o) placing a metallic mesh on top for reinforcing T-beams, and for setting pipes of at least plumbing, electrical lines, telephone lines, and television cable, and after reinforcement,
(p) pouring concrete over and finish the slab roof, leaving the supporting platform for a day, thereby is moved to the next construction site the following day to built a roof in one day,
(q) whereby, said wall form and said pipes are swiftly installed so costs are reduced in terms of paying hours work to the labor,
(r) whereby, said wall is not made of wood but relatively said concrete with said rocks or other material instead of said rocks costs are again reduced in terms of material cost.
II. The construction system of claim I wherein said using rock masonry, it is not constrained to said rocks since several other construction materials can be used instead of thereof, provided the material coheres well to concrete and thereof is a high percentage in volume of construction material used, thereby, possibilities are limitless, as ruble from a war zone or natural disasters, used tires, ginger bread, and numerous other materials can be used instead of said rock.
III. The precast items of claim I wherein said templates means for making said precast items' production automatic, thereby, as many as needed can be produced avoiding the precasts not being produced under specifications required, and the production done swiftly by unskilled labor.
IV. The wood molds of claim I wherein said opening of a building containing said opening selected from the group consisting of at least windows and doors, and panels of glass or any other materials.
V. The wood molds of claim I wherein said concrete shall have a compressive strength no less than 500 pounds per square inch.
VI. The concrete of claim V wherein said the compressive strength shall be tested for seven days.
VII. Pouring into said wood molds of claim I wherein said concrete shall be cured for at least twenty-eight days at a temperature above 50° F. without moving them, after pouring.
VIII. The reinforcing wherein said rebars form a structure with rod stirrups or hangers.
IX. The rebars of claim VIII wherein said rod stirrups mean stirrups of at least made of rods of one quarter inch less in diameter than said rebars, and in U-shape bents.
X. The rod stirrups of claim IX wherein said U-shape bents mean for holding said rebars with at least an 18 gauge twisted wire, and at distances of no more than four inches center to center.
XI. The exterior and interior wall molds of claim I wherein said drilling holes mean drilling at a dimension to let ties pass from end to end, and distance between the holes and number of said holes on the wall molds shall be according to width and height of hereof under engineering calculations, thereby size of the walls is not restricted.
XII. The perimeter of mold of claim I wherein said color code means for indicating unskilled labor where to dig said trenches, whereby, even the illiterate or foreigner labor can perform efficiently said digging.
XIII. The exterior wall molds of claim I wherein said color and graphic code means for indicating unskilled labor where to install the wall molds, whereby, even illiterate or overseas labor can execute erection of said wall molds by the book.
XIV. The precast of claim I wherein said return means nailed strips of a lumber of 2 inches thick by half of jamb's dimension minus width length, with a length equal to wall's height, set at a right angle to the interior face of exterior and interior wall molds.
XV. The precast of claim I wherein said return means for holding openings of a building and precast items, and a stop, as thereof shall outline the ends for concrete masonry in between openings.
XVI. The pouring into said walls of claim I wherein said concrete masonry mean about two feet height of concrete, for sinking into said concrete rocks of a dimension no greater than the thickness of said walls and pressing with sticks to accommodate into said concrete, and then repeating the same process of pouring said concrete and later said rocks until the wall forms are filled to the peak.
XVII. On top of walls of claim I wherein said a construction material containing the material selected from the group consisting of a steel structure of rebars and stirrups and trapezoidal pipes.
XVIII. The construction material of claim XVII wherein said steel structure of rebars and stirrups means for a roof or deck that shall be of concrete.
XIX. The construction material of claim XVII wherein said trapezoidal pipes mean for a roof or deck that shall be at least of metal or wood or joists trusses or rafters for holding connectors for roof's elements.
XX. On top of walls of claim I wherein said T-beams mean a reinforced concrete beam having a cross section resembling letter T.
XXI. The T-beams of claim XX wherein said reinforced concrete beam mean at least metal bars, rods, wires, or other slender members designed under structural engineering calculations and embedded into the concrete, thereby the metal structure and said concrete together resist at least forces from loads of living traffic, and wind, snow and other conditions imposed to roof
XXII. On top of platform of claim I wherein said material for providing temperature insulation containing the material selected from the group consisting of rigid insulation panels and hollow concrete blocks.
XXIII. The roof of claim I wherein said pouring concrete shall consider engineering calculations for stipulating the adequate proportions of Portland cement, sand, gravel, water and chemical additives necessary to move a supporting platform the day after the concrete pour.