A SIS identification method of reversible recovery fault-oriented workshop key manufacturing resources is that based on SIS model in the infectious disease research theory, the workpieces and manufacturing resources required in a production order are linked together through database technology to establish a discrete production workshop manufacturing network. The SIS model is configured to solve a change of the number of bottlenecks of other manufacturing resources caused by the initial fault manufacturing resources over time. The weighted result of a peak number of bottleneck resources and its time to reach the peak is marked to determine the importance of the initial fault manufacturing resources. Through the sorting of importance, the key manufacturing resource nodes in the discrete workshop are finally selected. The invention sorts out other key manufacturing resources that need to pay attention in production management in the manufacturing workshop to plan in advance and to improve the efficiency.
Get notified when new applications in this technology area are published.
G05B19/41865 » CPC further
Programme-control systems electric; Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM] characterised by job scheduling, process planning, material flow
G05B19/4188 » CPC further
Programme-control systems electric; Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM] characterised by CIM planning or realisation
G05B19/418 IPC
Programme-control systems electric Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM]
G05B19/4184 » CPC main
Programme-control systems electric; Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM] characterised by fault tolerance, reliability of production system
This is a non-provisional application that claims priority to a Chinese application, Chinese application number CN202110795439.8, filed Jul. 14, 2021, the entire contents of each of which are expressly incorporated herein by reference.
BACKGROUND OF THE PRESENT INVENTION Field of InventionThe present invention relates to a technical field of production processing control, and more particularly to a SIS identification method of reversible recovery fault-oriented workshop key manufacturing resources.
Description of Related ArtsDue to the dramatical market competitive, enterprises focus on the improvement and optimization of the production system and production process to meet the needs of different customers. The requirements for the efficient and controllable production system and manufacturing resources, such as personnel, machines, materials, and workpieces related to production activities, can be achieved by organic combination and mutual cooperation. Scientific and systematic analysis and quantitative evaluation of the production system is able to enhance the stability of discrete manufacturing workshops and improve the on-time completion rate of workpieces, so as to improve the economic efficiency of enterprises.
The provision of production system analysis is to fully understand and accurately model the production links of discrete manufacturing workshops. By establishing key indicators, risk points and key nodes of the production plan within a production cycle of the workshop can be identified, while accurate data can be provided and supported for subsequent targeted improvements.
SUMMARY OF THE PRESENT INVENTIONIn order to solve the above problems, an objective of the present invention is to provide a SIS identification method of reversible recovery fault-oriented workshop key manufacturing resources. First, through information technology and database technology, an automatic link of workpieces produced in a production cycle is established to link with their production plan, production process, and manufacturing resources. Second, according to SIS model in the infectious disease research theory, it is configured to have an initial âfault has been occurredâ manufacturing resource and a âfault has not been occurredâ manufacturing resource in discrete workshop manufacturing resources. Third, a change of a number of bottleneck of other manufacturing resources over a time is determined through the SIS model. Then, an importance of the initial âfault has been occurredâ manufacturing resource is marked by weighting a peak value of the number of bottleneck and a time length to reach the peak value. Next, groupings of the initial âfault has been occurredâ manufacturing resource and the âfault has not been occurredâ manufacturing resource in the workshop manufacturing resources are changed while the importance is re-determined. Repeat the steps until the importance of all possible groupings is obtained. Finally, key manufacturing resource nodes in the discrete workshop manufacturing system are obtained according to an order of all the importance.
According to the present invention, the foregoing and other objects and advantages are attained by:
a SIS identification method of reversible recovery fault-oriented workshop key manufacturing resources for establishing a production model comprises the steps, executed by a computerized device, such as a computer or a server, of:
Step 1: Based on Internet RFID technology and relational SQL database, establish an automatic link of workpieces produced in a production cycle with their production plan, production process, and manufacturing resources, and according to SIS model in the infectious disease research theory, assume a total number of the manufacturing resources as a constant as N throughout a production cycle of a manufacturing workshop, and configure an initial âfault has been occurredâ manufacturing resource and a âfault has not been occurredâ manufacturing resource in discrete workshop manufacturing resources as X(t0) and Y(t0) respectively.
Configure a relationship between X(t0) and Y(t0) as:
Step 2: Based on Internet RFID technology and relational SQL database, establish a second automatic link among the workpieces, the production plan, the production process, and the corresponding manufacturing resources within the production cycle in the manufacturing workshop. Convert the second automatic link into a plurality of connecting network edges in a workshop manufacturing system network. Finally map weighted edges of a processing time and all the manufacturing resources, including machine tools, cutting tools, fixtures, measuring tools and personnel in the production process, to a plurality of network nodes in the workshop manufacturing system network.
Step 3: According to a grouping result in the Step 1, configure a probability of eventual failure of the âfault has not been occurredâ manufacturing resource caused by the âfault has been occurredâ manufacturing resource as β, configure an effective number in unit of time for the âfault has not been occurredâ manufacturing resource to the âfault has been occurredâ manufacturing resource as Îł, and configure a ratio of a number of the âfault has been occurredâ manufacturing resource that has failed again to a total number of the âfault has been occurredâ manufacturing resource as Îť.
Step 4: As shown in FIG. 3, configure a fault propagation rate between the manufacturing resources with a connection relationship thereof as a ratio of the weight of the edge connecting two of the manufacturing resources and the maximum weight in the entire network. βij is determined as:
β i j = w i j w max δ
wherein δ is the contact probability of two of the manufacturing resources. The contact probability is set as 1 when there is a connecting edge between the two manufacturing resources. The contact probability is set as 0 when there is no connecting edge between the two manufacturing resources.
Step 5: Through the SIS model, determine a change of a number of bottleneck occurring over a time for the âfault has not been occurredâ manufacturing resource due to the initial the âfault has been occurredâ manufacturing resource.
I ( t ) = N ( Îť β â Îł ) Îť β ( N ( Îť β â Îł ) I 0 Îť β â 1 ) e â ( Îť β â Îł ) t + 1
wherein I(t) is the number of bottleneck occurring in the âfault has been occurredâ manufacturing resources over the time.
Step 6: Mark an importance of the initial âfault has been occurredâ manufacturing resource by weighting a peak value of the number of bottleneck and a time length to reach the peak value.
Z Y D ( i ) = k 1 T ( i ) + k 2 P ÂŻ ( i )
Step 7: As shown in FIG. 4, change groupings of the initial âfault has been occurredâ manufacturing resource and the âfault has not been occurredâ manufacturing resource in the workshop manufacturing resources and re-determine the importance according to steps 1 to 6, and repeat it until the importance of all possible groupings is obtained.
Step 8: Obtain key manufacturing resource nodes in the discrete workshop manufacturing system according to an order of all the importance, so as to establish the production model based on the key manufacturing resource nodes.
The present invention has the following advantages.
FIG. 1 is a block diagram illustrating a classification of workshop key manufacturing resources according to the present invention.
FIG. 2 is a block diagram illustrating a network building framework of workshop key manufacturing resources according to the present invention.
FIG. 3 illustrates values of contact probabilities for different manufacturing resources according to the present invention.
FIG. 4 is a flowchart illustrating key manufacturing resource node identification according to the present invention.
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTA SIS identification method of reversible recovery fault-oriented workshop key manufacturing resources is configured for establishing a production model, wherein the method comprises the following steps which are executed by a computerized device.
Step 1: As shown in FIG. 1, based on Internet RFID technology and relational SQL database, establish an automatic link of workpieces produced in a production cycle with their production plan, production process, and manufacturing resources, and according to SIS model in the infectious disease research theory, assume a total number of the manufacturing resources as a constant as N throughout a production cycle of a manufacturing workshop, and configure an initial âfault has been occurredâ manufacturing resource and a âfault has not been occurredâ manufacturing resource in discrete workshop manufacturing resources as X(t0) and Y(t0) respectively.
Configure a relationship between X(t0) and Y(t0) as:
Step 2: As shown in FIG. 2, based on Internet RFID technology and relational SQL database, establish a second automatic link among the workpieces, the production plan, the production process, and the corresponding manufacturing resources within the production cycle in the manufacturing workshop. Convert the second automatic link into a plurality of connecting network edges in a workshop manufacturing system network. Finally map weighted edges of a processing time and all the manufacturing resources, including machine tools, cutting tools, fixtures, measuring tools and personnel in the production process, to a plurality of network nodes in the workshop manufacturing system network.
Step 3: According to a grouping result in the Step 1, configure a probability of eventual failure of the âfault has not been occurredâ manufacturing resource caused by the âfault has been occurredâ manufacturing resource as β, configure an effective number in unit of time for the âfault has not been occurredâ manufacturing resource to the âfault has been occurredâ manufacturing resource as Îł, and configure a ratio of a number of the âfault has been occurredâ manufacturing resource that has failed again to a total number of the âfault has been occurredâ manufacturing resource as Îť.
Step 4: As shown in FIG. 3, configure a fault propagation rate between the manufacturing resources with a connection relationship thereof as a ratio of the weight of the edge connecting two of the manufacturing resources and the maximum weight in the entire network. βij is determined as:
β i j = w i j w max δ
wherein δ is the contact probability of two of the manufacturing resources. The contact probability is set as 1 when there is a connecting edge between the two manufacturing resources. The contact probability is set as 0 when there is no connecting edge between the two manufacturing resources.
Step 5: Through the SIS model, determine a change of a number of bottleneck occurring over a time for the âfault has not been occurredâ manufacturing resource due to the initial the âfault has been occurredâ manufacturing resource.
I ( t ) = N Îť β â Îł Îť β N Îť β â Îł I 0 Îť β â 1 e â Îť β â Îł t + 1
wherein I(t) is the number of bottleneck occurring in the âfault has been occurredâ manufacturing resources over the time.
Step 6: Mark an importance of the initial âfault has been occurredâ manufacturing resource by weighting a peak value of the number of bottleneck and a time length to reach the peak value.
Z Y D ( i ) = k 1 T ( i ) + k 2 P ÂŻ ( i )
Step 7: As shown in FIG. 4, change groupings of the initial âfault has been occurredâ manufacturing resource and the âfault has not been occurredâ manufacturing resource in the workshop manufacturing resources and re-determine the importance according to steps 1 to 6, and repeat it until the importance of all possible groupings is obtained.
Step 8: Obtain key manufacturing resource nodes in the discrete workshop manufacturing system according to an order of all the importance, so as to establish the production model based on the key manufacturing resource nodes. In other words, the production model can be accurately established by programming using the key manufacturing resource nodes so as to optimize the production system.
1. A SIS identification method of reversible recovery fault-oriented workshop key manufacturing resources for establishing a production model, comprising the steps, executed by a computerized device, of:
step 1: based on Internet RFID technology and relational SQL database, establishing an automatic link of workpieces produced in a production cycle with their production plan, production process, and manufacturing resources; according to SIS model in the infectious disease research theory, assuming a total number of the manufacturing resources as a constant as U throughout a production cycle of a manufacturing workshop, and configuring an initial âfault has been occurredâ manufacturing resource and a âfault has not been occurredâ manufacturing resource in discrete workshop manufacturing resources as X(t0) and Y(t0) respectively;
wherein a relationship between X(t0) and Y(t0) is configured as:
X t 0 = x 1 t 0 , x 2 t 0 , x 3 t 0 , ... , x j t 0
Y t 0 = y 1 t 0 , y 2 t 0 , y 3 t 0 , ... , y k t 0
wherein:
Xj(t0) is the jth initial âfault has been occurredâ manufacturing resource at the start time;
Yk(t0) is the kth initial âfault has not been occurredâ manufacturing resource at the start time;
step 2: based on Internet RFID technology and relational SQL database, establishing a second automatic link among the workpieces, the production plan, the production process, and the corresponding manufacturing resources within the production cycle in the manufacturing workshop; converting the second automatic link into a plurality of connecting network edges in a workshop manufacturing system network, and finally mapping weighted edges of a processing time and all the manufacturing resources, including machine tools, cutting tools, fixtures, measuring tools and personnel in the production process, to a plurality of network nodes in the workshop manufacturing system network;
step 3: according to a grouping result in the step 1, configuring a probability of eventual failure of the âfault has not been occurredâ manufacturing resource caused by the âfault has been occurredâ manufacturing resource as β, configuring an effective number in unit of time for the âfault has not been occurredâ manufacturing resource to the âfault has been occurredâ manufacturing resource as Îł, and configuring a ratio of a number of the âfault has been occurredâ manufacturing resource that has failed again to a total number of the âfault has been occurredâ manufacturing resource as Îť;
step 4: configuring a fault propagation rate between the manufacturing resources with a connection relationship thereof as a ratio of the weight of the edge connecting two of the manufacturing resources and the maximum weight in the entire network, wherein βij is determined as:
β i j = w i j w max δ
wherein δ is the contact probability of two of the manufacturing resources, wherein the contact probability is set as 1 when there is a connecting edge between the two manufacturing resources, wherein the contact probability is set as 0 when there is no connecting edge between the two manufacturing resources;
step 5: through the SIS model, determining a change of a number of bottleneck occurring over a time for the âfault has not been occurredâ manufacturing resource due to the initial the âfault has been occurredâ manufacturing resource;
I t = N Îť β â Îł Îť β N Îť β â Îł I 0 Îť β â 1 e â Îť β â Îł t + 1
wherein I(t) is the number of bottleneck occurring in the âfault has been occurredâ manufacturing resources over the time;
Step 6: marking an importance of the initial âfault has been occurredâ manufacturing resource by weighting a peak value of the number of bottleneck and a time length to reach the peak value;
Z Y D i = k 1 T i + k 2 P ÂŻ i
wherein ZYD(i) is the importance of the ith group of initial âfault has been occurredâ manufacturing resource;
T(i) is the peak time when the number of bottlenecks in the ith group reaches the peak value;
P(i) is the peak value of the number of bottleneck in the ith group;
k1, k2 are the weights of peak time and peak value;
step 7: changing groupings of the initial âfault has been occurredâ manufacturing resource and the âfault has not been occurredâ manufacturing resource in the workshop manufacturing resources and re-determine the importance according to steps 1 to 6, and repeat it until the importance of all possible groupings is obtained; and