US20120222375A1
2012-09-06
13/411,590
2012-03-04
A structural system comprised of prefabricated deck units spaced along longitudinal load-carrying members which produces longitudinal axial compression in deck units. During construction, prefabricated deck units are erected on top of and supported by the longitudinal load-carrying members via leveling devices, which also permit relative motion between the longitudinal load-carrying members and the prefabricated deck units. Anchor assemblies are affixed to the longitudinal load-carrying members near intermediate supports. Tensioned structural elements are installed in the anchor assemblies between spans and stressed to induce tension in the longitudinal load-carrying members and subsequently produce deck compression.
Get notified when new applications in this technology area are published.
E01D19/00 » CPC further
Structural or constructional details of bridges
E04B5/10 » CPC further
Floors; Floor construction with regard to insulation; Connections specially adapted therefor; Load-carrying floor structures formed substantially of prefabricated units with metal beams or girders, e.g. with steel lattice girders
E04B5/43 » CPC further
Floors; Floor construction with regard to insulation; Connections specially adapted therefor Floor structures of extraordinary design; Features relating to the elastic stability; Floor structures specially designed for resting on columns only, e.g. mushroom floors
E01D2101/285 » CPC further
Material constitution of bridges; Concrete, stone or stone-like material; Concrete reinforced prestressed Composite prestressed concrete-metal
E04B1/02 IPC
Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
E04B5/02 IPC
Floors; Floor construction with regard to insulation; Connections specially adapted therefor Load-carrying floor structures formed substantially of prefabricated units
E04B7/00 IPC
Roofs; Roof construction with regard to insulation
E01D19/12 » CPC main
Structural or constructional details of bridges Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
E01D21/00 » CPC further
Methods or apparatus specially adapted for erecting or assembling bridges
This application claims the benefit of U.S. Provisional Application No. 61/449,713, filed Mar. 6, 2011 by the present inventor.
Not Applicable
Not Applicable
1. Field of Invention
This invention relates to the design and construction of structures, specifically to structures with prefabricated deck units.
2. Prior Art
Full-depth precast concrete deck has gained popularity as an accelerated construction method. Use of full-depth precast concrete deck allows for the deck concrete and reinforcement to be placed in a controlled environment, improving the quality of the deck. Since the units are prefabricated, they can be delivered to a site and erected quickly.
Structures using full-depth precast concrete deck typically consist of a plurality of longitudinally spaced concrete deck units supported by longitudinal load-carrying members. This member or members is usually a single girder or multiple girders.
This member or members can be comprised of various materials including steel, concrete, wood or fiber-reinforced plastic.
To improve deck durability, it is important to have a pre-compression force across deck joints to minimize the propensity of the deck to crack under loading.
Currently, such pre-compression force is supplied via standard post-tensioning systems, which utilize post-tensioning tendons or bars within ducts. US Federal Highway Administration technical report (#FHWA-IF-09-010) and Precast/Prestressed Concrete institute State-of-the-Art Report on Full-Depth Precast Concrete Bridge Deck Panels (SOA-01-1911) provide a comprehensive summary of current engineering practice using precast deck units, showing that all current precast deck systems with longitudinal compression utilize post-tensioning systems in the deck. Other patent references, such as U.S. Pat. No. 7,475,446, U.S. Pat. No. 7,461,427, and U.S. Pat. No. 5,457,839, teach various methods of using post-tensioning systems to provide deck compression. However, using standard post-tensioning details carries with it the disadvantage of requiring additional cost and time to construct. This invention provides a more economical solution.
U.S. Pat. No. 7,475,446 B1, by the present inventor, teaches a solution to introduce pre-compression force across deck joints via post-tensioning external to the deck, using a method to transfer longitudinal compression to the deck units under the following conditions:
The proposed method discussed herein also provides a solution to introduce pre-compression force across deck joints via post-tensioning external to the deck, but 65 applies the following differing conditions from those presented in U.S. Pat. No. 7,475,446:
Therefore, the method proposed herein eliminates the need for special end deck units to be fabricated and allows for a substantially reduced quantity of tensioned structural elements to be employed versus that presented in U.S. Pat. No. 7,475,446.
U.S. application Ser. No. 12/857,713, by the present inventor, teaches a solution to introduce pre-compression force across deck joints via post-tensioning external to the deck, using a method to transfer longitudinal compression to the deck units under the following condition:
The proposed method discussed herein also provides a solution to introduce precompression force across deck joints via post-tensioning external to the deck, but applies the following differing condition from those presented in U.S. application Ser. No. 12/857,713:
Therefore, the method proposed herein does not require post-tensioning tendons running along or within the majority of the length of the supporting girders to provide longitudinal compression to the deck panels, as presented in U.S. application Ser. No. 12/857,713.
U.S. application Ser. No. 12/963,233, by the present inventor, teaches a solution to introduce pre-compression force across deck joints via tensioning the supporting girders themselves under the following condition:
The proposed method discussed herein also provides a solution to introduce pre-compression force across deck joints via tensioning the supporting girders themselves, but applies the following differing condition from those presented in U.S. application Ser. No. 12/963,233:
Therefore, the method proposed herein does not require the use of jacks placed within gaps in the deck as presented in U.S. application Ser. No. 12/963,233.
Accordingly, several objects and advantages of the present invention are to provide a structural system that:
Further objects and advantages will become apparent from a consideration of the ensuing description and drawings.
In accordance with the present invention a structural construction system comprises prefabricated deck units spaced along longitudinal load-carrying members. Axial compression of these prefabricated deck units is produced by external tensioned elements anchored in anchor assemblies integrated with the longitudinal load carrying members at intermediate support locations. The prefabricated deck panels are fitted with means to react against the longitudinal load-carrying members.
FIG. 1 shows the elevation view of an example bridge used to describe the present invention.
FIG. 2 shows the plan view of the example bridge.
FIG. 3 shows the general cross section of the example bridge.
FIG. 4 shows the plan view of a typical deck unit.
FIG. 4A shows the bulkhead view of a typical deck unit.
FIG. 4B shows the transverse cross-section of a typical deck unit.
FIG. 4C shows the section of a shear key at a typical deck joint.
FIG. 4D shows the detail of shear connectors and void for shear connectors.
FIG. 5 shows mechanism to apply deck compression force.
FIGS. 6A-6B show examples of girder connections at the median pier.
FIG. 7 shows an example girder connection at the median pier for an alternate embodiment using concrete girders.
A preferred embodiment of the bridge construction system of the present invention is illustrated in FIGS. 1 through 5 in the context of a two-span bridge, hereinafter referred to as “example bridge”. The example bridge has two abutments 12 and an intermediate pier 13 acting as substructure units. The preferred embodiment of the bridge construction system is comprised of steel girders 11 acting as longitudinal load-carrying members, precast concrete deck units 18 acting as prefabricated deck units. The precast concrete deck units can be constructed using long or short line match-casting or without match-casting.
However, those features comprising the structural construction system mentioned in the preferred embodiment and the substructure and span arrangement mentioned above can have various embodiments not mentioned in the preferred embodiment, as discussed in detail hereinafter and as will become apparent from a consideration of the ensuing description and drawings.
Steel girders 11 are placed on and supported by abutments 12 and pier 13. Steel girders 11 are of fabricated plate girders, but may be of any suitable structural shape, such as tub girders, rolled beams, trusses, etc. Bearing stiffeners 51 typical to such support configurations are provided. A gap 22 between the girder ends at the pier 13 is provided to allow for relative movement between the steel girders 11 of each span. On top of girders 11, a plurality of leveling devices is placed to support the precast deck units 18 that also allows for relative longitudinal motion between girders 11 and the precast concrete deck units 18. In the preferred embodiment, the leveling devices are comprised of shims, however leveling bolts or other devices that can provide support for the deck and allow for relative longitudinal motion between girders 11 and the precast concrete deck units 18 can be used. As will be evident from the description hereinafter, this allowance for relative motion will allow for the precast concrete deck units to be compressed by reacting to the tensioning of girders 11. Shims may be of steel, plastic, elastomeric materials, teflon-based or teflon-impregnated materials, etc.
A plurality of voids 28, similar to those used in conventional precast deck placement, are provided in deck units 18 above girders 11 to allow for mechanical connection of deck units 18 to girders 11 while shear connectors voids 28 are grouted. Haunches 30 will also be grouted at the same time as the shear connector voids 28. Shear connectors shall be detailed to allow relative motion between precast concrete deck units 18 and girders 11 during the precast concrete deck unit erection process and prior to grouting, as hereinafter described. In the preferred embodiment, shear connectors are shear studs 26 welded to the girders 11.
Deck joints 20 between adjacent precast concrete deck units can be of the match-cast type, with or without epoxy, or cast-in-place using concrete, grout or other suitable jointing materials. In the preferred embodiment, match-cast epoxy joints are used.
In the preferred embodiment, anchor assemblies 34 are fabricated with the girders at the ends of the girders supported on the pier 13, as shown in FIG. 5. Post-tensioning bars 33 acting as tensioned structural elements are placed within the anchor assemblies 34. The deck connection unit 32 at each end of the bridge 245 is made composite prior to any stressing of the post-tensioning bars 33 so that the deck connection unit 34 will act as a mounted element that can react the deck compression with girder tension that results from stressing post-tensioning bars 33. FIG. 6A and FIG. 6B show that the anchor assemblies 34 consist of stiffeners 35 and anchor plates 37.
In the preferred embodiment, the girder connection at the pier location is simply supported for dead load and continuous for live load. This is achieved by making the girder bottom flange connection at pier after all dead loads are applied to the structure. FIG. 6A and FIG. 6B show examples of the girder connection at the median pier. The tensile transfer connection near the top of the girder is made through the post-tensioning bars 33. When only the post-tensioning bar connection is made, the girder acts as simply supported in bending moment but can transfer axial tension. The girder becomes continuous in transferring moment when both bottom flange and the tensile transfer connections are made. FIG. 6A shows simply-supported connection configuration and FIG. 67B shows an alternate to connect bottom flanges with high strength filler material 54 placed between bottom flange connection plates 52. By connecting the bottom flanges, the girder system will act as continuous under subsequently applied loads.
Alternate embodiments for the present invention are described hereinafter:
The preferred embodiment in the context of the example bridge is illustrated hereinafter.
Abutments 12 and pier 13 are constructed. Girders 11 are erected with anchor assemblies 34 pre-installed. A gap 22 between the girder ends at the pier 13 is provided to allow for relative movement between the steel girders 11 of each span.
The girder top elevation is then surveyed and the shim thickness at each supporting point calculated so as to provide the correct setting elevations for deck units. Shims are placed on top of the girders. Post-tensioning bars 33 are installed within the anchor assemblies 34 in conjunction with bearing plates 36 and nuts 38. Post-tensioning bars 33 are not stressed at this stage.
Precast deck units 18 are erected, placing one unit adjacent to the previously erected one and applying epoxy to the adjacent faces of the two units. Means is employed to provide a certain amount of compression over the epoxy joint (typically at 40 psi, similar to segmental bridge construction) to ensure the joint is properly set. This process is repeated until all deck units 18 are installed.
After all deck units are installed, deck connection units 32 are made composite with the supporting girders by grouting the shear connector voids 28 and the haunches 30 relative to the deck connection units. The post-tensioning bars 33 are then stressed. The nuts 38 are tightened against the bearing plates 36 and anchor plates 37 in conjunction with the stressing operations to lock in the stress in the post-tensioning bars 33.
After the stressing of the post-tensioning bars 33, shear connector voids 28 and haunches of all remaining deck units are grouted.
As an option, the girder bottom flange connection at the median pier 13 may then made so that the girder connection at pier location will function as continuous under subsequently applied loads. This is accomplished by placing high strength filler 54 between the bottom flange connection plates 52.
The operational description above is particular to the preferred embodiment of the present invention in the context of the two-span bridge heretofore defined. Alternate materials, member shapes, connection types at the median piers, means of stressing, etc. can be used in employing the structural construction system of the present invention.
The present invention provides a structural system that eliminates many of the drawbacks found in current precast deck construction associated with standard longitudinal post-tensioning. Notably, it offers an alternate to provide pre-compression across joints of precast deck units without employment of post-tensioning tendons and associated ducts in the deck. This significantly reduces the cost and time of construction required.
Beyond simply providing a system that eliminates the drawbacks in current precast deck construction, the present invention can potentially increase the load carrying capacity of longitudinal load-carrying members by employing appropriate connection details at the median pier, and correct construction steps. In the preferred embodiment, the stressing of the post-tensioning bars introduces a negative moment at the midspan of the girders, which offsets part of the girder moment under service load.
In conclusion, the present invention provides a structural construction system utilizing prefabricated deck units that is durable, easy to construct and cost-effective. The present invention can accommodate a variety of structural configurations and can be rapidly constructed.
Although the description above contains many specificities, these should not be construed as limiting the scope of the invention but as merely providing illustrations of some of the presently preferred embodiments of this invention. For example, as illustrated and described herein, the present invention can accommodate a variety of jacking methods and details, a variety of girder connection methods, and a variety of shapes and materials for longitudinal load-carrying members.
Thus the scope of the invention should be determined by the appended claims and their legal equivalents, rather than by the examples given.
1. A structural system, comprising:
a. a plurality of longitudinal load-carrying members,
b. a plurality of prefabricated deck units spaced longitudinally along a structure, wherein said prefabricated deck units are supported by said longitudinal load-carrying members,
c. one or more intermediate supports upon which said longitudinal load-carrying members are partially supported, whereby a plurality of longitudinal load carrying member spans are defined,
d. one or more anchor assemblies affixed to said longitudinal load-carrying members in a region in proximity to said intermediate supports,
e. one or more tensioned structural elements installed into said anchor assemblies to introduce longitudinal axial compression to a plurality of said prefabricated deck units, wherein said axial compression is a result of the application of longitudinal axial tension to said longitudinal load-carrying members, wherein no separate longitudinal post-tensioning elements are required in the deck, and wherein no direct jacking of said prefabricated deck units is required to introduce said longitudinal axial compression,
f. means to allow for relative movement between a plurality of said longitudinal load-carrying members at a time at which tensioning is applied to said tensioned structural element or elements,
g. means to transfer said longitudinal axial tension in said longitudinal load-carrying members to axial compression to a plurality of said prefabricated deck units.
2. The means to allow for relative movement of claim 1 (f) is comprised of a physical gap of predetermined width between the longitudinal load-carrying members of claim 1 that lie along the same longitudinal line but in different spans, wherein said spans are as defined in claim 1 (c).
3. The means to transfer axial tension of claim 1 (g) is comprised of a plurality of mounted elements affixed to the longitudinal load-carrying members of claim 1 in-between which are located a plurality of prefabricated deck units of claim 1 that are non-composite with the longitudinal bad-carrying members of claim 1 at the time of the tensioning of claim 1 (f).
4. The mounted elements of claim 3 are comprised of a plurality of prefabricated deck units of claim 1 that are composite with the longitudinal bad-carrying members of claim 1, whereby said composite prefabricated deck units act as deck connection units.
5. The structure of cairn 1 is comprised of one or more structural units, wherein the longitudinal axial compression of claim 1 may be introduced into the prefabricated deck units of claim 1 in any one of said structural units independent of any other one or more of said structural units.
6. The longitudinal load-carrying members of claim 1 are comprised of any one member or any combination of members selected from the group consisting of steel, concrete, wood, and composite materials.
7. The longitudinal load-carrying members of claim 1 are comprised of any one member or any combination of members selected from the group consisting of I-girders, I-beams, box girders, and trusses.
8. The tensioned structural element or elements of claim 1 are comprised of any one member or any combination of members selected from the group consisting of high strength bars, post-tensioning rods, steel plates and post-tensioning tendons.
9. A method for constructing one or more structural units wherein no separate longitudinal post-tensioning elements are required in the deck, comprising the steps of:
a. constructing a plurality of prefabricated deck units, a plurality of supports for the structure, a plurality of longitudinal bad-carrying members, a plurality of anchor assemblies, wherein said assemblies are affixed to said longitudinal bad-carrying members in regions to be in proximity with intermediate instances of said supports, a plurality of mounted elements, and a plurality of tensioned structural elements,
b. installing said longitudinal load-carrying member or members, wherein said longitudinal load-carrying members are supported by said supports,
c. installing said tensioned structural elements into said anchor assemblies
d. installing a plurality of said prefabricated deck units, wherein said prefabricated deck units are supported by said longitudinal load-carrying members and rest on devices that permit relative motion between said prefabricated deck units and said longitudinal load-carrying members, wherein said prefabricated deck units are non-composite with said longitudinal load-carrying members,
e. installing a plurality of mounted elements, wherein a plurality of said prefabricated units are located in-between said mounted elements,
f. stressing said tensioned structural elements to introduce axial compression in said prefabricated deck units, wherein said axial compression is a result of the application of longitudinal axial tension to said longitudinal load-carrying member or members,
g. making said non-composite prefabricated deck units composite with said longitudinal load-carrying members.
10. The longitudinal load-carrying members of claim 9 are comprised of any one member or any combination of members selected from the group consisting of steel, concrete, wood, and composite materials.
11. The longitudinal load-carrying members of claim 9 are comprised of any one member or any combination of members selected from the group consisting of I-girders, I-beams, box girders, and trusses.